Macy’s at the Aventura Mall

Facing a demolition-build addition to Macy’s at the Aventura Mall, Beck Concrete was tasked with creative problem solving. The parking lot needed to be removed and, in its place, a new building pad poured before construction could begin.

Working with the client, Beck Concrete packaged services to efficiently meet the needs of the general contractor. The asphalt parking lot, curbs, and sidewalks were selectively demolished. Beck immediately started the import of 4 cubic tons of compactable fill to form the building pad of the 23,000-square-foot addition.

Our experience and problem solving mindset allows us to swiftly meet challenges with creative solutions.

The parking lot needed to be removed and, in its place, a new building pad poured before construction could begin.